The city's contractor, Pawtucket Hot Mix Asphalt Inc. (PHMA), will begin paving operations, weather dependent, the week of May 3. The streets include Tryon Ave., Gibbs St., and Little St. These streets will be milled and paved. Utility covers will be adjusted to grade. Work will begin a 7 am. During construction the roads may be closed, except for local traffic. Motor vehicle access to residents' properties may be limited or restricted for brief periods of time during construction. The hours of construction will typically be from 7 a.m. until 5 p.m. Monday through Friday, although longer hours and weekend work may be required to complete the project in a timely manner. Temporary “NO PARKING” signs will be posted along these roads and will be enforced during the hours of construction. Parking will be permitted outside of construction hours.
Work will begin on Kelly Avenue and Washburn Avenue beginning May 6th. These streets will be reclaimed, graded and paved.